Refurbishments, extensions, new shopfronts and changes of layout often leave the gas meter in the wrong place. It might be in the way of new walls, inside a room that is being converted or somewhere the meter operator can no longer safely reach. A commercial gas meter relocation is a common job, but who does it and how long it takes depends on how far the meter is moving.
Short Moves Versus Moving the Service

There are broadly two kinds of meter move.
Moving the meter on the existing service
If the meter only moves a short distance and the incoming service pipe and emergency control valve stay where they are, the job is usually handled by the supplier’s Meter Asset Manager working with a Gas Safe registered engineer. This is the quicker route.
Moving the point where gas enters the building
If the new meter position needs the service pipe rerouted, or the emergency control valve moved, the gas network (Cadent, SGN, Northern Gas Networks or Wales and West Utilities) has to alter its service. That means a quote, a survey and often excavation, so it takes longer and costs more.
Rules for a New Meter Position
- It must be safely accessible for reading, maintenance and emergencies
- It needs to be in a well ventilated position, away from ignition sources
- It should not be under stairs or in escape routes where a leak would block exit
- External meter boxes or housings are often preferred on commercial sites
- The engineer and meter operator must agree the position before work is booked
Agreeing the position early avoids the most common problem, which is a meter visit that has to be abandoned because the chosen spot is not acceptable.
How Long Does a Meter Relocation Take?
| Type of move | Typical time |
|---|---|
| Meter moved on existing service | 2 to 6 weeks to arrange |
| Service alteration by the network | 2 to 3 months or more |
| Move combined with a meter upgrade | Plan as a new service |
If the meter needs to move and grow at the same time, for example because the refurbishment adds a kitchen or boiler, treat it as a service upgrade from the outset. Our guide to commercial gas meter sizes explains how to check the load.
What Drives the Cost

- Whether the network’s service pipe has to be altered
- The distance and route between old and new positions
- Excavation, reinstatement and any highway permits
- New meter housings or boxes
- Internal pipework changes by your Gas Safe engineer
A short move on the existing service is a fraction of the cost of a service alteration, so it is worth asking whether a nearby position would work before committing to a larger move.
Plan It Into the Refurbishment Programme
Raise the meter position at design stage, alongside electricity, water and drainage. Gas work often has the longest lead time of any service, and it can hold up a fit out that is otherwise ready. If the building is being stripped out entirely, consider whether a temporary removal and a new connection later is simpler; our guide to gas meter removal and disconnection covers that route.
How E for Energy Helps
We find out whether the move needs the network or just the meter operator, get the quotes, agree the meter position and keep each party to your programme. Because a supplier must be registered for any meter work, we also check the supply contract is in place and competitive. See our business gas meter installation page for how it works.
Frequently Asked Questions
Can I move a gas meter myself?
No. Gas meter and pipework work must be carried out by the appropriate companies: the meter operator for the meter, the gas network for the service and a Gas Safe registered engineer for pipework.
Who pays to move a commercial gas meter?
The business or property owner requesting the move normally pays. The network quotes for service alterations; the meter operator and your engineer charge for their parts of the work.
Can a gas meter be moved outside?
Often yes, and external meter boxes are common on commercial sites. Moving it outside usually means altering where the service enters, so it may need the network.
Will the gas be off while the meter is moved?
Yes, for part of the work. Plan it for a quiet period, and for schools a holiday, so heating and catering are not affected.